Services Status

Recent Events

Sub-services Impacted:

  • 200G - BCT - MIA

Status: Planned

Action Date: March 11, 2026, 4 a.m.

Current Status Information: In Process

The provider will be conducting a low risk power maintenance on its power systems in Boca Raton, FL. Although no impact for this circuit is expected, this maintenance is deemed potentially service affecting.

Start: March 11th 2026 03:00 UTC

End: March 11th 2026 10:00 UTC

Service Impact: None expected; backup paths are in place in case of outage.

Sub-services Impacted:

  • 100G - FTZ - MIA

Status: Planned

Action Date: Feb. 28, 2026, 5 a.m.

Current Status Information: Completed

The provider will be conducting mandatory fiber maintenance in Miami, FL.

Start: February 28th 2026 05:00 UTC

End: March 1st 2026 01:00 UTC

Estimated Duration of Maintenance: 20 Hours (Estimated 0 minutes of downtime)

Service Impact: None expected

Sub-services Impacted:

  • 200G - BCT - MIA

Status: Planned

Action Date: Feb. 28, 2026, 5 a.m.

Current Status Information: Completed

The provider will be conducting maintenance for mandatory cable relocation.

Start: February 28th 2026 05:00 UTC

End: March 1st 2026 01:00 UTC

Estimated Duration of Maintenance: Up to 20 Hours

Service Impact: None expected; backup paths are in place.

Sub-services Impacted:

  • 100G - MIA - JAX - Primary

Status: Planned

Action Date: March 3, 2026, 5 a.m.

Current Status Information: Completed

The provider will be conducting maintenance to replace fiber cables between Orlando and DeLeon Springs.

Start: March 3rd 2026 05:00 UTC

End: March 3rd 2026 11:00 UTC

Estimated Duration of Maintenance: 5 Hours

Service Impact: None expected; backup paths are in place.

A backup window from March 4th 2026 05:00 UTC to March 4th 2026 11:00 UTC is reserved if necessary.


Legend

In Process

Alert

Outage

Planned