11-07-2024 09:13 a.m.

11-07-2024 02:32 p.m.

Started: 11-07-2024 09:13 a.m.

Ended: 11-07-2024 02:32 p.m.

The listed asset is currently suffering an outage. Our provider has been contacted. Backup services are being utilized.

11-04-2024 12:30 p.m.

11-05-2024 06:12 p.m.

Started: 11-04-2024 12:30 p.m.

Ended: 11-05-2024 06:12 p.m.

The listed asset is suffering an outage. We are contacting the provider and are awaiting updates.

10-02-2024 10:00 p.m.

10-03-2024 11:59 a.m.

Started: 10-02-2024 10:00 p.m.

Ended: 10-03-2024 11:59 a.m.

A maintenance window for one of Ampath/AmLight's commodity internet service providers for interface physical cleaning will exist. Due to the redundancy in place, no outage is expected.

09-26-2024 08:17 p.m.

09-28-2024 05:49 p.m.

Started: 09-26-2024 08:17 p.m.

Ended: 09-28-2024 05:49 p.m.

Multiple flaps affecting the link between San Juan and Panama. 

09-09-2024 11:29 a.m.

09-10-2024 02:12 p.m.

Started: 09-09-2024 11:29 a.m.

Ended: 09-10-2024 02:12 p.m.

The listed asset is currently suffering an outage. Provider has been contacted. Updates will be provided as they come.

09-05-2024 01:05 p.m.

09-05-2024 01:17 p.m.

Started: 09-05-2024 01:05 p.m.

Ended: 09-05-2024 01:17 p.m.

The listed asset is suffering an outage. Backup services are being utilized. Provider is being contacted for updates.

09-03-2024 01:17 p.m.

09-05-2024 09:09 a.m.

Started: 09-03-2024 01:17 p.m.

Ended: 09-05-2024 09:09 a.m.

The listed asset is currently suffering from an outage. Provider has been contacted. Backup services are being utilized.

08-28-2024 10:54 a.m.

08-28-2024 02:17 p.m.

Started: 08-28-2024 10:54 a.m.

Ended: 08-28-2024 02:17 p.m.

The listed asset has suffered instability and flapped within the given time. Our provider is being contacted for an RFO.

08-05-2024 11:17 a.m.

08-27-2024 02:33 p.m.

Started: 08-05-2024 11:17 a.m.

Ended: 08-27-2024 02:33 p.m.

The listed asset is currently suffering an outage. Provider has been contacted and updates will be given as they come.

07-22-2024 02:06 p.m.

07-23-2024 11:00 a.m.

Started: 07-22-2024 02:06 p.m.

Ended: 07-23-2024 11:00 a.m.

The listed asset is currently suffering an outage. Provider has been contacted. Updates will be provided as they come. Backup services are being utilized.

04-23-2024 04:43 a.m.

04-23-2024 04:54 a.m.

Started: 04-23-2024 04:43 a.m.

Ended: 04-23-2024 04:54 a.m.

We faced an outage on the 100G link between FTZ and CPT.

04-23-2024 12:27 p.m.

04-23-2024 12:27 p.m.

Started: 04-23-2024 12:27 p.m.

Ended: 04-23-2024 12:27 p.m.

We faced a brief outage on the 100G link between MIA and SJU.

04-15-2024 08:32 a.m.

04-15-2024 04:56 p.m.

Started: 04-15-2024 08:32 a.m.

Ended: 04-15-2024 04:56 p.m.

The listed asset is down and the provider has been contacted. The RFO and ETR is unknown at this time.

03-21-2024 01:00 a.m.

03-21-2024 05:00 a.m.

Started: 03-21-2024 01:00 a.m.

Ended: 03-21-2024 05:00 a.m.

CHG0077044 AMPATH: Upgrading Santiago PoP - MW 3/3

AMPATH Engineers will remove legacy devices in Santiago and install the next generation of equipment. During these maintenance windows, we expect network services to face minimal outages when moving physical connections. 

03-20-2024 01:00 a.m.

03-20-2024 09:00 a.m.

Started: 03-20-2024 01:00 a.m.

Ended: 03-20-2024 09:00 a.m.

CHG0077043 AMPATH: Upgrading Santiago PoP - MW 2/3

AMPATH Engineers will remove legacy devices in Santiago and install the next generation of equipment. During these maintenance windows, we expect network services to face minimal outages when moving physical connections. 

03-19-2024 01:00 a.m.

03-19-2024 09:00 a.m.

Started: 03-19-2024 01:00 a.m.

Ended: 03-19-2024 09:00 a.m.

Maintenance CHG0077041 - AMPATH: Upgrading Santiago PoP - MW 1/3

AMPATH Engineers will remove legacy devices in Santiago and install the next generation of equipment. During these maintenance windows, we expect network services to face minimal outages when moving physical connections. 

12-01-2023 09:07 a.m.

12-01-2023 09:21 a.m.

Started: 12-01-2023 09:07 a.m.

Ended: 12-01-2023 09:21 a.m.

We are facing an outage on the 100G link between Panama and Chile.

08-08-2023 12:07 p.m.

08-09-2023 09:03 a.m.

Started: 08-08-2023 12:07 p.m.

Ended: 08-09-2023 09:03 a.m.

An outage is currently affecting the listed assets. Provider is being contacted. Updates will be provided as they come.

08-04-2023 03:10 p.m.

08-04-2023 10:00 p.m.

Started: 08-04-2023 03:10 p.m.

Ended: 08-04-2023 10:00 p.m.

An outage is currently affecting the listed assets. Updates will be given after the provider gives more information.

08-04-2023 03:10 p.m.

08-04-2023 10:00 p.m.

Started: 08-04-2023 03:10 p.m.

Ended: 08-04-2023 10:00 p.m.

An outage is currently affecting the listed assets. Updates will be given after the provider gives more information.

08-31-2023 10:00 p.m.

09-01-2023 08:00 a.m.

Started: 08-31-2023 10:00 p.m.

Ended: 09-01-2023 08:00 a.m.

The AMPATH/AmLight team will migrate the Boca Raton rack. Increased latency is expected for certain connectors. The entire window is reserved.

08-31-2023 10:00 p.m.

09-01-2023 08:00 a.m.

Started: 08-31-2023 10:00 p.m.

Ended: 09-01-2023 08:00 a.m.

The AMPATH/AmLight team will migrate the Boca Raton rack. Increased latency is expected for certain connectors. The entire window is reserved.

08-30-2023 10:00 p.m.

08-31-2023 08:00 a.m.

Started: 08-30-2023 10:00 p.m.

Ended: 08-31-2023 08:00 a.m.

The AMPATH/AmLight team will migrate the Boca Raton rack. Increased latency is expected for certain connectors. The entire window is reserved.

08-30-2023 10:00 p.m.

08-31-2023 08:00 a.m.

Started: 08-30-2023 10:00 p.m.

Ended: 08-31-2023 08:00 a.m.

The AMPATH/AmLight team will migrate the Boca Raton rack. Increased latency is expected for certain connectors. The entire window is reserved.

08-10-2023 03:00 a.m.

08-10-2023 09:00 a.m.

Started: 08-10-2023 03:00 a.m.

Ended: 08-10-2023 09:00 a.m.

Work will be done on the circuit BocaRaton - Fortaleza (Monet) to change the frequencies of the transponders. The circuit will be impacted, but backup services will be utilized. The entire window is reserved. This is a backup maintenance window to be used if the original window fails to be executed successfully under CHG0070790.

08-04-2023 03:00 a.m.

08-04-2023 09:00 a.m.

Started: 08-04-2023 03:00 a.m.

Ended: 08-04-2023 09:00 a.m.

Work will be done on the circuit BocaRaton - Fortaleza (Monet) to change the frequencies of the transponders. The circuit will be impacted, but backup services will be utilized. The entire window is reserved.

07-19-2023 02:00 a.m.

07-19-2023 10:00 a.m.

Started: 07-19-2023 02:00 a.m.

Ended: 07-19-2023 10:00 a.m.

CHG0070365 - AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-19-2023 02:00 a.m.

07-19-2023 10:00 a.m.

Started: 07-19-2023 02:00 a.m.

Ended: 07-19-2023 10:00 a.m.

CHG0070365 - AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-19-2023 02:00 a.m.

07-19-2023 10:00 a.m.

Started: 07-19-2023 02:00 a.m.

Ended: 07-19-2023 10:00 a.m.

CHG0070365 - AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-18-2023 02:00 a.m.

07-18-2023 10:00 a.m.

Started: 07-18-2023 02:00 a.m.

Ended: 07-18-2023 10:00 a.m.

CHG0070368 - MW AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-18-2023 02:00 a.m.

07-18-2023 10:00 a.m.

Started: 07-18-2023 02:00 a.m.

Ended: 07-18-2023 10:00 a.m.

CHG0070368 - MW AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-18-2023 02:00 a.m.

07-18-2023 10:00 a.m.

Started: 07-18-2023 02:00 a.m.

Ended: 07-18-2023 10:00 a.m.

CHG0070368 - MW AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-18-2023 02:00 a.m.

07-18-2023 10:00 a.m.

Started: 07-18-2023 02:00 a.m.

Ended: 07-18-2023 10:00 a.m.

CHG0070368 - MW AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-18-2023 02:00 a.m.

07-18-2023 10:00 a.m.

Started: 07-18-2023 02:00 a.m.

Ended: 07-18-2023 10:00 a.m.

CHG0070368 - MW AMPATH Physical migration FIU035WMI2CRPNN - There will be a Maintenance Window on one of Ampath/AmLight's Commodity Internet service providers for a physical migration. Impact is expected, the backup services will be utilized.

07-06-2023 03:00 a.m.

07-06-2023 09:00 a.m.

Started: 07-06-2023 03:00 a.m.

Ended: 07-06-2023 09:00 a.m.

Work will be done on the circuit to change the frequencies of the transponders. The circuit will be impacted, but backup services will be utilized. The entire window is reserved.

06-16-2023 12:06 p.m.

06-17-2023 08:19 a.m.

Started: 06-16-2023 12:06 p.m.

Ended: 06-17-2023 08:19 a.m.

The listed asset is currently suffering an outage. Our provider has been contacted and no RFO or ETR is given as of yet. WIll update as details come.

05-10-2023 04:02 p.m.

05-11-2023 12:18 a.m.

Started: 05-10-2023 04:02 p.m.

Ended: 05-11-2023 12:18 a.m.

The Crown Castle Fibers between Miami and Boca Raton are currently down. Updates will be provided as they come.

04-17-2023 01:42 p.m.

04-17-2023 06:42 p.m.

Started: 04-17-2023 01:42 p.m.

Ended: 04-17-2023 06:42 p.m.

A major fiber event took place on the listed asset and the provider is assessing the damage. No ETR as of yet. Updates will be given as they come.

04-17-2023 01:42 p.m.

04-17-2023 06:42 p.m.

Started: 04-17-2023 01:42 p.m.

Ended: 04-17-2023 06:42 p.m.

A major fiber event took place on the listed asset and the provider is assessing the damage. No ETR as of yet. Updates will be given as they come.

03-16-2023 01:17 p.m.

03-17-2023 10:25 a.m.

Started: 03-16-2023 01:17 p.m.

Ended: 03-17-2023 10:25 a.m.

 The link (FIU035WMI2CRPNN) between Miami and San Juan is DOWN.

INC0135621:59 Outage - AMPATH Provider LANautilus FIU035WMI2CRPNN

 

03-06-2023 11:35 a.m.

03-06-2023 08:04 p.m.

Started: 03-06-2023 11:35 a.m.

Ended: 03-06-2023 08:04 p.m.

INC0134794:59 Outage - AMPATH Provider LANautilus FIU035WMI2CRPNN. We contacted LANautilus for RFO.

03-03-2023 12:01 p.m.

03-03-2023 05:50 p.m.

Started: 03-03-2023 12:01 p.m.

Ended: 03-03-2023 05:50 p.m.

An outage is ongoing for the listed assets. Updates will be provided.

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-28-2023 08:00 p.m.

02-28-2023 11:59 p.m.

Started: 02-28-2023 08:00 p.m.

Ended: 02-28-2023 11:59 p.m.

The AmLight team will execute a planned maintenance window to enable OESS' orchestration of the services on FOR-LAN-SW02 and FOR-ACB-SW01.

Short outages are expected on services with an endpoint in Fortaleza. The entire window is reserved. 

02-09-2023 10:00 p.m.

02-10-2023 01:00 a.m.

Started: 02-09-2023 10:00 p.m.

Ended: 02-10-2023 01:00 a.m.

CHG0066219  - Upgrade the firmware of SAO-SP4-SW03 and BCT-MI3-SW02

02-01-2023 10:00 p.m.

02-02-2023 02:00 a.m.

Started: 02-01-2023 10:00 p.m.

Ended: 02-02-2023 02:00 a.m.

The AMPATH team will be doing to migrate and maintain some FLR VLANs. Services may be impacted.

02-01-2023 10:00 p.m.

02-02-2023 02:00 a.m.

Started: 02-01-2023 10:00 p.m.

Ended: 02-02-2023 02:00 a.m.

The AMPATH team will be doing to migrate and maintain some FLR VLANs. Services may be impacted.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-22-2022 11:00 p.m.

11-23-2022 02:00 a.m.

Started: 11-22-2022 11:00 p.m.

Ended: 11-23-2022 02:00 a.m.

The AMPATH team needs to do a migration inside the RedClara OOB network. OOB access may be impacted during the MW.

11-03-2022 10:38 a.m.

11-04-2022 02:00 a.m.

Started: 11-03-2022 10:38 a.m.

Ended: 11-04-2022 02:00 a.m.

The listed asset is currently suffering from an outage. Updates will be provided as they come.

11-03-2022 10:38 a.m.

11-04-2022 02:00 a.m.

Started: 11-03-2022 10:38 a.m.

Ended: 11-04-2022 02:00 a.m.

The listed asset is currently suffering from an outage. Updates will be provided as they come.

11-03-2022 10:38 a.m.

11-04-2022 02:00 a.m.

Started: 11-03-2022 10:38 a.m.

Ended: 11-04-2022 02:00 a.m.

The listed asset is currently suffering from an outage. Updates will be provided as they come.

10-28-2022 06:42 a.m.

10-28-2022 01:27 p.m.

Started: 10-28-2022 06:42 a.m.

Ended: 10-28-2022 01:27 p.m.

The listed asset is unavailable. The provider is currently investigating for an RFO. Backup services will be utilized.

10-28-2022 06:42 a.m.

10-28-2022 01:27 p.m.

Started: 10-28-2022 06:42 a.m.

Ended: 10-28-2022 01:27 p.m.

The listed asset is unavailable. The provider is currently investigating for an RFO. Backup services will be utilized.

10-28-2022 06:42 a.m.

10-28-2022 01:27 p.m.

Started: 10-28-2022 06:42 a.m.

Ended: 10-28-2022 01:27 p.m.

The listed asset is unavailable. The provider is currently investigating for an RFO. Backup services will be utilized.

10-11-2022 11:00 p.m.

10-12-2022 02:00 a.m.

Started: 10-11-2022 11:00 p.m.

Ended: 10-12-2022 02:00 a.m.

Fiber cable work is needed to ensure the integrity of the links. Backup services will be utilized.

10-04-2022 05:34 p.m.

10-05-2022 04:14 p.m.

Started: 10-04-2022 05:34 p.m.

Ended: 10-05-2022 04:14 p.m.

A failed card is currently causing an outage. Technicians are moving to replace the card. No ETR as of yet. Backup services are being utilized.

09-16-2022 10:00 p.m.

09-17-2022 12:00 a.m.

Started: 09-16-2022 10:00 p.m.

Ended: 09-17-2022 12:00 a.m.

The AMPATH team needs to work on a reconfiguration. Backup services will be utilized.

09-08-2022 03:48 p.m.

09-08-2022 06:48 p.m.

Started: 09-08-2022 03:48 p.m.

Ended: 09-08-2022 06:48 p.m.

The listed asset is currently suffering an outage. AMPATH engineers are actively investigating. Updates will be provided as they come.

08-02-2022 10:00 p.m.

08-03-2022 02:00 a.m.

Started: 08-02-2022 10:00 p.m.

Ended: 08-03-2022 02:00 a.m.

The listed assets will be undergoing maintenance for reconfiguration. Backup services will be utilized.

08-02-2022 10:00 p.m.

08-03-2022 02:00 a.m.

Started: 08-02-2022 10:00 p.m.

Ended: 08-03-2022 02:00 a.m.

The listed assets will be undergoing maintenance for reconfiguration. Backup services will be utilized.

08-01-2022 10:00 p.m.

08-02-2022 02:00 a.m.

Started: 08-01-2022 10:00 p.m.

Ended: 08-02-2022 02:00 a.m.

The listed assets will be undergoing maintenance for reconfiguration. Backup services will be utilized.

07-19-2022 06:00 a.m.

07-19-2022 02:30 p.m.

Started: 07-19-2022 06:00 a.m.

Ended: 07-19-2022 02:30 p.m.

The 100G backup link between Miami and Jacksonville is down. Our provider was contacted. A planned maintenance window was supposed to finish at 6 am EST, but we continue to see our link down. This ticket will be updated as soon as we get more information from our provider. 

The services are up and using the primary path. 

07-19-2022 06:00 a.m.

07-19-2022 02:30 p.m.

Started: 07-19-2022 06:00 a.m.

Ended: 07-19-2022 02:30 p.m.

The 100G backup link between Miami and Jacksonville is down. Our provider was contacted. A planned maintenance window was supposed to finish at 6 am EST, but we continue to see our link down. This ticket will be updated as soon as we get more information from our provider. 

The services are up and using the primary path. 

07-13-2022 08:47 a.m.

07-13-2022 02:06 p.m.

Started: 07-13-2022 08:47 a.m.

Ended: 07-13-2022 02:06 p.m.

The listed asset is suffering instability. Updates will be provided as they come. Backup services are being utilized.

07-06-2022 01:38 a.m.

07-09-2022 12:10 p.m.

Started: 07-06-2022 01:38 a.m.

Ended: 07-09-2022 12:10 p.m.

The listed asset is currently having availability issues. Backup services are being utilized. Updates will be provided as they come.

06-18-2022 10:00 a.m.

06-18-2022 06:00 p.m.

Started: 06-18-2022 10:00 a.m.

Ended: 06-18-2022 06:00 p.m.

The AmLight team is working on installing a new programmable switch in the environment. Backup services will be utilized. 

06-18-2022 10:00 a.m.

06-18-2022 06:00 p.m.

Started: 06-18-2022 10:00 a.m.

Ended: 06-18-2022 06:00 p.m.

The AmLight team is working on installing a new programmable switch in the environment. Backup services will be utilized. 

06-01-2022 12:04 a.m.

06-01-2022 05:20 a.m.

Started: 06-01-2022 12:04 a.m.

Ended: 06-01-2022 05:20 a.m.

The 100G link between San Juan and Miami is down. The services were switched to their backup path. 

05-18-2022 04:30 p.m.

05-19-2022 03:50 p.m.

Started: 05-18-2022 04:30 p.m.

Ended: 05-19-2022 03:50 p.m.

The listed asset is currently suffering instability. Updates will be provided as they come.

05-19-2022 10:00 p.m.

05-20-2022 02:00 a.m.

Started: 05-19-2022 10:00 p.m.

Ended: 05-20-2022 02:00 a.m.

The AmLight team will execute a maintenance window to migrate the link FIU035WMI2CRPNN (100G link between SanJuan and Miami) to a new device in Miami.
 
Outages are anticipated during the migration, and the entire window is reserved. Services with redundancy will be switched to the backup path.

05-11-2022 10:00 p.m.

05-12-2022 07:00 a.m.

Started: 05-11-2022 10:00 p.m.

Ended: 05-12-2022 07:00 a.m.

Our provider will execute a maintenance window for a hardware replacement on a submarine segment. Work is required to maintain the stability of the network. The links below will be affected. The services with a backup path will be switched to the other side of the ring.

 

100G link between Santiago and Panama City

10G link between Santiago and Miami

05-10-2022 10:00 p.m.

05-11-2022 07:00 a.m.

Started: 05-10-2022 10:00 p.m.

Ended: 05-11-2022 07:00 a.m.

Our provider will execute a maintenance window for a hardware replacement on a submarine segment. Work is required to maintain the stability of the network. The links below will be affected. The services with a backup path will be switched to the other side of the ring.

 

100G link between Santiago and Panama City

10G link between Santiago and Miami

05-09-2022 10:00 p.m.

05-10-2022 07:00 a.m.

Started: 05-09-2022 10:00 p.m.

Ended: 05-10-2022 07:00 a.m.

Our provider will execute a maintenance window for a hardware replacement on a submarine segment. Work is required to maintain the stability of the network. The links below will be affected. The services with a backup path will be switched to the other side of the ring.

 

100G link between Santiago and Panama City

10G link between Santiago and Miami

05-08-2022 10:00 p.m.

05-09-2022 07:00 a.m.

Started: 05-08-2022 10:00 p.m.

Ended: 05-09-2022 07:00 a.m.

Our provider will execute a maintenance window for a hardware replacement on a submarine segment. Work is required to maintain the stability of the network. The links below will be affected. The services with a backup path will be switched to the other side of the ring.

 

100G link between Santiago and Panama City

10G link between Santiago and Miami

05-05-2022 02:31 p.m.

05-06-2022 02:48 a.m.

Started: 05-05-2022 02:31 p.m.

Ended: 05-06-2022 02:48 a.m.

The listed asset is currently suffering an outage. Backup services are being utilized. Engineers have been contacted and updates will be provided as they come.

05-05-2022 12:41 a.m.

05-05-2022 06:35 a.m.

Started: 05-05-2022 12:41 a.m.

Ended: 05-05-2022 06:35 a.m.

The 100G link between Santiago and Panama is down. Our provider was contacted. The services were switched to their backup paths.

05-04-2022 09:49 a.m.

05-04-2022 09:50 a.m.

Started: 05-04-2022 09:49 a.m.

Ended: 05-04-2022 09:50 a.m.

The listed asset has suffered a brief outage. Updates will be provided as they arrive.

05-03-2022 10:32 a.m.

05-03-2022 10:32 a.m.

Started: 05-03-2022 10:32 a.m.

Ended: 05-03-2022 10:32 a.m.

The listed asset was briefly unavailable. LANautilus Engineers have been contacted to investigate. Updates on the link brief outages will be provided as they come.

05-03-2022 09:55 a.m.

05-03-2022 09:56 a.m.

Started: 05-03-2022 09:55 a.m.

Ended: 05-03-2022 09:56 a.m.

The listed asset was briefly unavailable. LANautilus Engineers have been contacted to investigate. Updates on the link brief outages will be provided as they come.

04-22-2022 10:00 p.m.

04-23-2022 07:00 a.m.

Started: 04-22-2022 10:00 p.m.

Ended: 04-23-2022 07:00 a.m.

Our provider needs to work on a hardware replacement for the submarine segment. Backup services will be utilized.

04-21-2022 10:00 p.m.

04-22-2022 07:00 a.m.

Started: 04-21-2022 10:00 p.m.

Ended: 04-22-2022 07:00 a.m.

Our provider needs to work on a hardware replacement for the submarine segment. Backup services will be utilized.

04-20-2022 10:00 p.m.

04-21-2022 07:00 a.m.

Started: 04-20-2022 10:00 p.m.

Ended: 04-21-2022 07:00 a.m.

Our provider needs to work on a hardware replacement for the submarine segment. Backup services will be utilized.

04-19-2022 10:00 p.m.

04-20-2022 07:00 a.m.

Started: 04-19-2022 10:00 p.m.

Ended: 04-20-2022 07:00 a.m.

Our provider needs to work on a hardware replacement for the submarine segment. Backup services will be utilized.

04-18-2022 10:00 p.m.

04-19-2022 07:00 a.m.

Started: 04-18-2022 10:00 p.m.

Ended: 04-19-2022 07:00 a.m.

Our provider needs to work on a hardware replacement for the submarine segment. Backup services will be utilized.

04-07-2022 02:51 p.m.

04-08-2022 02:01 a.m.

Started: 04-07-2022 02:51 p.m.

Ended: 04-08-2022 02:01 a.m.

The FLR optical backbone circuit between Miami and Tampa is down.

Affected services include:
FLRnet Tampa-Miami 100G MPLS backbone
FLRnet Miami flex node to Tampa core node connection
City of Boca Raton secondary FLR connection
University of Miami secondary FLR connection
Ampath secondary FLR connection to TPA
Awave 100G wave Miami to Jacksonville, secondary path
FIU to NWRDC VLAN 2 L2VPN
FL-IX Tampa peering connection

04-07-2022 02:51 p.m.

04-08-2022 02:01 a.m.

Started: 04-07-2022 02:51 p.m.

Ended: 04-08-2022 02:01 a.m.

The FLR optical backbone circuit between Miami and Tampa is down.

Affected services include:
FLRnet Tampa-Miami 100G MPLS backbone
FLRnet Miami flex node to Tampa core node connection
City of Boca Raton secondary FLR connection
University of Miami secondary FLR connection
Ampath secondary FLR connection to TPA
Awave 100G wave Miami to Jacksonville, secondary path
FIU to NWRDC VLAN 2 L2VPN
FL-IX Tampa peering connection

02-02-2022 03:31 p.m.

02-03-2022 09:15 p.m.

Started: 02-02-2022 03:31 p.m.

Ended: 02-03-2022 09:15 p.m.

The listed asset is currently experiencing an outage. The backup links are being used.

02-02-2022 03:31 p.m.

02-03-2022 09:15 p.m.

Started: 02-02-2022 03:31 p.m.

Ended: 02-03-2022 09:15 p.m.

The listed asset is currently experiencing an outage. The backup links are being used.

02-02-2022 03:31 p.m.

02-03-2022 09:15 p.m.

Started: 02-02-2022 03:31 p.m.

Ended: 02-03-2022 09:15 p.m.

The listed asset is currently experiencing an outage. The backup links are being used.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

12-09-2021 12:00 a.m.

01-31-2022 12:00 a.m.

Started: 12-09-2021 12:00 a.m.

Ended: 01-31-2022 12:00 a.m.

AmLight/AMPATH is aware of the Apache Zero-Day Log4j vulnerability, first reported publicly on December 9, 2021, as well as subsequent log4j vulnerabilities. To date, AmLight/AMPATH has observed no Indicators of Compromise (IOC) in either our network infrastructure or supporting systems. AmLight/AMPATH is proactively monitoring, investigating, and responding to threats that may impact the Academic/Commodity network. In addition, we are working closely with our connectors, vendors, and service providers to identify the potential impact and to ensure their organizations have initiated containment, investigations, and mitigation plans addressing this vulnerability and any other potential cyber threat.

11-15-2021 10:42 a.m.

11-16-2021 03:43 a.m.

Started: 11-15-2021 10:42 a.m.

Ended: 11-16-2021 03:43 a.m.

The listed asset is currently suffering an outage. Backup services are being utilized.

11-16-2021 12:00 a.m.

11-16-2021 06:00 a.m.

Started: 11-16-2021 12:00 a.m.

Ended: 11-16-2021 06:00 a.m.

LUMEN engineers need to perform maintenance. 

11-03-2021 11:50 a.m.

11-04-2021 11:14 a.m.

Started: 11-03-2021 11:50 a.m.

Ended: 11-04-2021 11:14 a.m.

The specified link is currently suffering an outage. Backup services are currently being utilized. Updates will be provided.

11-03-2021 11:50 a.m.

11-04-2021 11:14 a.m.

Started: 11-03-2021 11:50 a.m.

Ended: 11-04-2021 11:14 a.m.

The specified link is currently suffering an outage. Backup services are currently being utilized. Updates will be provided.

11-21-2021 06:00 a.m.

11-21-2021 12:00 p.m.

Started: 11-21-2021 06:00 a.m.

Ended: 11-21-2021 12:00 p.m.

Our provider needs to perform traffic affecting work in order to rectify a fault. Backup services will be utilized.

10-14-2021 05:26 a.m.

10-14-2021 02:27 p.m.

Started: 10-14-2021 05:26 a.m.

Ended: 10-14-2021 02:27 p.m.

The listed asset is currently unavailable. Backup services are currently being utilized. Updates will be provided as they come.

09-29-2021 10:00 a.m.

09-29-2021 11:00 a.m.

Started: 09-29-2021 10:00 a.m.

Ended: 09-29-2021 11:00 a.m.

Work needs to be completed on the link in order to move the service from a current card to a new one. Backup services will be utilized.

09-27-2021 02:50 p.m.

09-27-2021 03:50 p.m.

Started: 09-27-2021 02:50 p.m.

Ended: 09-27-2021 03:50 p.m.

Loss of connectivity was detected between Santiago - La Serena. The main link is down. The issue is under investigation. 

 

09-27-2021 02:50 p.m.

09-27-2021 03:50 p.m.

Started: 09-27-2021 02:50 p.m.

Ended: 09-27-2021 03:50 p.m.

Loss of connectivity was detected between Santiago - La Serena. The main link is down. The issue is under investigation. 

 

09-27-2021 02:50 p.m.

09-27-2021 03:50 p.m.

Started: 09-27-2021 02:50 p.m.

Ended: 09-27-2021 03:50 p.m.

Loss of connectivity was detected between Santiago - La Serena. The main link is down. The issue is under investigation. 

 

08-16-2021 01:27 p.m.

08-16-2021 01:27 p.m.

Started: 08-16-2021 01:27 p.m.

Ended: 08-16-2021 01:27 p.m.

The connection between São Paulo and Miami flapped. The services were switched to another path. 

08-03-2021 11:23 a.m.

08-03-2021 12:06 p.m.

Started: 08-03-2021 11:23 a.m.

Ended: 08-03-2021 12:06 p.m.

The listed asset is unavailable, and suffering a major outage. We are moving services to backup links. LANautilus Engineers have been contacted. Updates will be provided when they are available.

08-03-2021 11:23 a.m.

08-03-2021 12:06 p.m.

Started: 08-03-2021 11:23 a.m.

Ended: 08-03-2021 12:06 p.m.

The listed asset is unavailable, and suffering a major outage. We are moving services to backup links. LANautilus Engineers have been contacted. Updates will be provided when they are available.

08-05-2021 10:00 p.m.

08-06-2021 06:00 a.m.

Started: 08-05-2021 10:00 p.m.

Ended: 08-06-2021 06:00 a.m.

Our provider is currently going to perform hardware replacements in the environment. 

08-04-2021 10:00 p.m.

08-05-2021 06:00 a.m.

Started: 08-04-2021 10:00 p.m.

Ended: 08-05-2021 06:00 a.m.

Our provider is currently going to perform hardware replacements in the environment. 

08-03-2021 10:00 p.m.

08-04-2021 06:00 a.m.

Started: 08-03-2021 10:00 p.m.

Ended: 08-04-2021 06:00 a.m.

Our provider is currently going to perform hardware replacements in the environment. 

08-02-2021 10:00 p.m.

08-03-2021 06:00 a.m.

Started: 08-02-2021 10:00 p.m.

Ended: 08-03-2021 06:00 a.m.

Our provider is currently going to perform hardware replacements in the environment. 

08-28-2021 12:00 a.m.

08-28-2021 08:00 p.m.

Started: 08-28-2021 12:00 a.m.

Ended: 08-28-2021 08:00 p.m.

Our provider will execute a maintenance window in the 100G link between Miami and Boca Raton.

The services will be switched to the backup fiber. 

07-16-2021 03:07 a.m.

07-16-2021 03:42 a.m.

Started: 07-16-2021 03:07 a.m.

Ended: 07-16-2021 03:42 a.m.

The 100G link between Santiago and Panama City is down. The services were migrated to the backup path. Our provider was contacted, but no reason for the outage was informed yet.

07-16-2021 07:00 a.m.

07-16-2021 08:00 a.m.

Started: 07-16-2021 07:00 a.m.

Ended: 07-16-2021 08:00 a.m.

AmLight network team will perform a maintenance window in Boca Raton to replace a switch. Due to the redundance in place, no outage is expected other than a few flaps due to the path change process.

06-08-2021 06:24 p.m.

06-09-2021 08:44 a.m.

Started: 06-08-2021 06:24 p.m.

Ended: 06-09-2021 08:44 a.m.

The listed service is currently unavailable.Our provider has sent engineers to investigate the issue. The reason for outage will be provided in later updates.

06-02-2021 06:49 a.m.

06-03-2021 09:59 a.m.

Started: 06-02-2021 06:49 a.m.

Ended: 06-03-2021 09:59 a.m.

The listed asset is unavailable following a outage. The reason for the outage is being investigated. Updates will be provided as they are received.

06-26-2021 12:00 a.m.

06-26-2021 11:45 p.m.

Started: 06-26-2021 12:00 a.m.

Ended: 06-26-2021 11:45 p.m.

Our provider needs to perform a maintenance on the link for the alotted time. Updates on reasons will be provided later.

05-25-2021 12:00 a.m.

05-25-2021 08:00 a.m.

Started: 05-25-2021 12:00 a.m.

Ended: 05-25-2021 08:00 a.m.

Work is required to perform infrastructure maintenance on core equipment.

04-20-2021 03:00 a.m.

04-20-2021 08:00 a.m.

Started: 04-20-2021 03:00 a.m.

Ended: 04-20-2021 08:00 a.m.

A scheduled work will be carried out in Colombia, to replace damaged card

04-19-2021 03:00 a.m.

04-19-2021 08:00 a.m.

Started: 04-19-2021 03:00 a.m.

Ended: 04-19-2021 08:00 a.m.

A scheduled work will be carried out in Colombia, to replace damaged card

04-13-2021 12:00 a.m.

04-13-2021 06:00 a.m.

Started: 04-13-2021 12:00 a.m.

Ended: 04-13-2021 06:00 a.m.

Work is required to perform infrastructure maintenance on core equipment to ensure the continued integrity of the network.

04-01-2021 09:00 p.m.

04-01-2021 10:00 p.m.

Started: 04-01-2021 09:00 p.m.

Ended: 04-01-2021 10:00 p.m.

The FLR 100Gb link will be unavailable while AMPATH Engineers perform a maintenance. AMPATH Engineers will perform the migration of the FLR 100Gb link to a new switch. Due to the redundancy in place, no outages are expected.

04-01-2021 09:00 p.m.

04-01-2021 10:00 p.m.

Started: 04-01-2021 09:00 p.m.

Ended: 04-01-2021 10:00 p.m.

The FLR 100Gb link will be unavailable while AMPATH Engineers perform a maintenance. AMPATH Engineers will perform the migration of the FLR 100Gb link to a new switch. Due to the redundancy in place, no outages are expected.

03-30-2021 10:00 p.m.

03-30-2021 10:30 p.m.

Started: 03-30-2021 10:00 p.m.

Ended: 03-30-2021 10:30 p.m.

AmLight/AMPATH network engineers in coordination with UPR network engineers will conduct a maintenance window to improve the redundancy on some of the BGP VLANs for Academic and Commodity transit. Only the redundant BGP sessions with UPR will be impacted, no service disruption is expected.

03-30-2021 10:00 p.m.

03-30-2021 10:30 p.m.

Started: 03-30-2021 10:00 p.m.

Ended: 03-30-2021 10:30 p.m.

AmLight/AMPATH network engineers in coordination with UPR network engineers will conduct a maintenance window to improve the redundancy on some of the BGP VLANs for Academic and Commodity transit. Only the redundant BGP sessions with UPR will be impacted, no service disruption is expected.

03-30-2021 10:00 p.m.

03-30-2021 10:30 p.m.

Started: 03-30-2021 10:00 p.m.

Ended: 03-30-2021 10:30 p.m.

AmLight/AMPATH network engineers in coordination with UPR network engineers will conduct a maintenance window to improve the redundancy on some of the BGP VLANs for Academic and Commodity transit. Only the redundant BGP sessions with UPR will be impacted, no service disruption is expected.

03-30-2021 10:00 p.m.

03-30-2021 10:30 p.m.

Started: 03-30-2021 10:00 p.m.

Ended: 03-30-2021 10:30 p.m.

AmLight/AMPATH network engineers in coordination with UPR network engineers will conduct a maintenance window to improve the redundancy on some of the BGP VLANs for Academic and Commodity transit. Only the redundant BGP sessions with UPR will be impacted, no service disruption is expected.

03-30-2021 10:00 p.m.

03-30-2021 10:30 p.m.

Started: 03-30-2021 10:00 p.m.

Ended: 03-30-2021 10:30 p.m.

AmLight/AMPATH network engineers in coordination with UPR network engineers will conduct a maintenance window to improve the redundancy on some of the BGP VLANs for Academic and Commodity transit. Only the redundant BGP sessions with UPR will be impacted, no service disruption is expected.

03-24-2021 07:09 a.m.

03-24-2021 03:11 p.m.

Started: 03-24-2021 07:09 a.m.

Ended: 03-24-2021 03:11 p.m.

The 100G link between San Juan and Miami is down. The services were switched to the backup path. Our provider was contacted.

03-23-2021 03:00 a.m.

03-23-2021 08:00 a.m.

Started: 03-23-2021 03:00 a.m.

Ended: 03-23-2021 08:00 a.m.

A scheduled work will be carried out in Colombia, to replace damaged card.

03-22-2021 03:00 a.m.

03-22-2021 08:00 a.m.

Started: 03-22-2021 03:00 a.m.

Ended: 03-22-2021 08:00 a.m.

A scheduled work will be carried out in Colombia to replace a damaged card. 

02-13-2021 04:00 a.m.

02-13-2021 09:00 a.m.

Started: 02-13-2021 04:00 a.m.

Ended: 02-13-2021 09:00 a.m.

An emergency work will be carried out in Panama, for OTDR measurements in the segment

02-13-2021 04:00 a.m.

02-13-2021 09:00 a.m.

Started: 02-13-2021 04:00 a.m.

Ended: 02-13-2021 09:00 a.m.

An emergency work will be carried out in Panama, for OTDR measurements in the segment

02-13-2021 04:00 a.m.

02-13-2021 09:00 a.m.

Started: 02-13-2021 04:00 a.m.

Ended: 02-13-2021 09:00 a.m.

An emergency work will be carried out in Panama, for OTDR measurements in the segment

02-14-2021 04:00 a.m.

02-14-2021 09:00 a.m.

Started: 02-14-2021 04:00 a.m.

Ended: 02-14-2021 09:00 a.m.

An emergency work will be carried out in Panama, for OTDR measurements in the segment

02-14-2021 04:00 a.m.

02-14-2021 09:00 a.m.

Started: 02-14-2021 04:00 a.m.

Ended: 02-14-2021 09:00 a.m.

An emergency work will be carried out in Panama, for OTDR measurements in the segment

02-14-2021 04:00 a.m.

02-14-2021 09:00 a.m.

Started: 02-14-2021 04:00 a.m.

Ended: 02-14-2021 09:00 a.m.

An emergency work will be carried out in Panama, for OTDR measurements in the segment

01-18-2021 11:04 a.m.

01-19-2021 08:45 a.m.

Started: 01-18-2021 11:04 a.m.

Ended: 01-19-2021 08:45 a.m.

The link between Miami and Boca Raton is unstable. The services were switched to the backup path. According to our provider, they are working to repair the fiber.

01-23-2021 12:00 a.m.

01-25-2021 06:00 a.m.

Started: 01-23-2021 12:00 a.m.

Ended: 01-25-2021 06:00 a.m.

Crown Castle Fiber will be conducting required maintenance at one of the links between Miami-BocaRaton for a fiber damage repair. Due to the redundancy in place, no outage is expected.

01-17-2021 12:00 a.m.

01-17-2021 08:00 p.m.

Started: 01-17-2021 12:00 a.m.

Ended: 01-17-2021 08:00 p.m.

Crown Castle Fiber will be conducting required maintenance at one of the links between Miami-BocaRaton for a fiber damage repair. Due to the redundancy in place, no outage is expected.

12-06-2020 12:00 a.m.

12-06-2020 05:00 a.m.

Started: 12-06-2020 12:00 a.m.

Ended: 12-06-2020 05:00 a.m.

Crown Castle will be conducting required maintenance at one of the fibers between Miami and Boca Raton. The services will be switched to the other fiber. No outages are expected.

11-17-2020 12:00 a.m.

11-17-2020 06:00 a.m.

Started: 11-17-2020 12:00 a.m.

Ended: 11-17-2020 06:00 a.m.

Crown Castle Fiber will be conducting required maintenance at one of the links between Miami-BocaRaton for a fiber damage repair. Due to the redundancy in place, no outage is expected.

10-25-2020 08:00 a.m.

10-30-2020 06:04 a.m.

Started: 10-25-2020 08:00 a.m.

Ended: 10-30-2020 06:04 a.m.

The peers with Tenet and UbuntuNet are down. The problem is being investigated.

Update 2020-10-26 07:48 ET: According to Tenet and UbuntuNet peers, the fault is related to a local issue (fiber issue).

Update 2020-10-28 15:15 ET: According to Tenet and UbuntuNet peers, the ETA is tomorrow (29/Oct/2020)

10-08-2020 04:50 p.m.

10-08-2020 04:50 p.m.

Started: 10-08-2020 04:50 p.m.

Ended: 10-08-2020 04:50 p.m.

The 100G link between Santiago and Panama flapped briefly. The services were switched to the backup path. 

10-06-2020 07:27 a.m.

10-06-2020 07:28 a.m.

Started: 10-06-2020 07:27 a.m.

Ended: 10-06-2020 07:28 a.m.

The link between Miami and San Juan went down for a minute. The services were switched to the other side of the ring during the outage. Our provider was contacted but no reason for the outage was found yet.

10-09-2020 10:00 p.m.

10-10-2020 02:00 a.m.

Started: 10-09-2020 10:00 p.m.

Ended: 10-10-2020 02:00 a.m.

AmLight team will execute a Maintenance Window for migrating the VLANs from MIA-MI1-SW02’s eth1/11 (MCT02) to use OpenFlow.

10-09-2020 10:00 p.m.

10-10-2020 02:00 a.m.

Started: 10-09-2020 10:00 p.m.

Ended: 10-10-2020 02:00 a.m.

AmLight team will execute a Maintenance Window for migrating the VLANs from MIA-MI1-SW02’s eth1/11 (MCT02) to use OpenFlow.

09-25-2020 03:09 p.m.

09-25-2020 03:09 p.m.

Started: 09-25-2020 03:09 p.m.

Ended: 09-25-2020 03:09 p.m.

The 100G link between Santiago and Panama flapped. The services were switched to the backup path. 

09-25-2020 02:38 p.m.

09-25-2020 02:38 p.m.

Started: 09-25-2020 02:38 p.m.

Ended: 09-25-2020 02:38 p.m.

The 100G link between Miami and San Juan flapped. The services were switched to the backup path. 

09-24-2020 02:55 p.m.

09-24-2020 02:57 p.m.

Started: 09-24-2020 02:55 p.m.

Ended: 09-24-2020 02:57 p.m.

The backup link for Academic Access to Internet2 went down for a few minutes. The primary link was stable during this time and no service was impacted. The reason for the outage is pending.

09-30-2020 11:00 p.m.

10-01-2020 05:00 a.m.

Started: 09-30-2020 11:00 p.m.

Ended: 10-01-2020 05:00 a.m.

The LANautilus team will execute a maintenance window that will impact the links below. The services will be switched to the other side of the ring. No impacts are expected.

- 10G link - Santiago x Miami

- 100G link - Parana x Santiago

09-19-2020 06:00 a.m.

09-19-2020 10:00 a.m.

Started: 09-19-2020 06:00 a.m.

Ended: 09-19-2020 10:00 a.m.

The LANautilus team will execute a maintenance window that will impact the links below. The services will be switched to the other side of the ring. No impacts are expected.

- 10G link - Santiago x Miami

- 100G link - Parana x Santiago

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

09-16-2020 09:32 a.m.

09-16-2020 09:39 a.m.

Started: 09-16-2020 09:32 a.m.

Ended: 09-16-2020 09:39 a.m.

The 100G Monet link between Miami and São Paulo was flapping for a couple of minutes. The provider was contacted but the reason for the outage was not informed yet. All services were switched to the backup path.

08-10-2020 03:23 p.m.

08-10-2020 09:56 p.m.

Started: 08-10-2020 03:23 p.m.

Ended: 08-10-2020 09:56 p.m.

The link between Panamá and Santiago is down. The provider was informed but no estimated time to return was informed yet. All VLANs with backup paths were switched to the other side of the ring.

08-10-2020 11:00 p.m.

08-11-2020 02:01 a.m.

Started: 08-10-2020 11:00 p.m.

Ended: 08-11-2020 02:01 a.m.

The provider will have maintenance to migrate the backhaul between Miami and Boca Raton to a new network, to improve reliability and network stability.

Duration of Maintenance (minutes): the entire time slot is reserved

Location : Boca Raton and Miami, FL

06-30-2020 01:00 a.m.

06-30-2020 03:00 a.m.

Started: 06-30-2020 01:00 a.m.

Ended: 06-30-2020 03:00 a.m.

The service provider will execute a maintenance window to perform a migration of aerial segments on Balboa, Panama. The link between Santiago and Miami must suffer flaps during the activity. All services with backup path will be automatically switched to it. 

06-12-2020 11:16 a.m.

06-12-2020 07:03 p.m.

Started: 06-12-2020 11:16 a.m.

Ended: 06-12-2020 07:03 p.m.

The 100G connection between Santiago and Panama is down. All services with redundancy were switched to the other side of the ring. No ETR informed yet. 

06-08-2020 09:34 a.m.

06-08-2020 09:32 p.m.

Started: 06-08-2020 09:34 a.m.

Ended: 06-08-2020 09:32 p.m.

A fiber cut between Miami and Boca Raton is impacting the connection between Miami and São Paulo and Miami to South Africa.

The dark fiber operator is working on the issue. No ETR was provided. 

04-24-2020 04:20 p.m.

05-21-2020 01:31 p.m.

Started: 04-24-2020 04:20 p.m.

Ended: 05-21-2020 01:31 p.m.

We faced a fiber cut in the connection from Miami to Boca. Local engineers were engaged.

04-20-2020 05:00 a.m.

04-20-2020 10:00 a.m.

Started: 04-20-2020 05:00 a.m.

Ended: 04-20-2020 10:00 a.m.

Dummy ticket - Multiple flaps affecting the link between San Juan and Parana City. Users will backup services will be redirected

04-22-2020 01:00 a.m.

04-22-2020 06:33 p.m.

Started: 04-22-2020 01:00 a.m.

Ended: 04-22-2020 06:33 p.m.

A fiber cut on CrownCastle fiber is affecting the connectivity from Boca Raton to Miami.